STUDY OF THE HYDROELECTRIC POTENTIAL OF THE SMALL HYDROELECTIC STATION PLANNED FOR VANDAM CHAY, GABALA REGION

Authors

  • Valiyev Jalaladdin Author

DOI:

https://doi.org/10.58225/sw.2024.2-122-127

Keywords:

sprinkler, displacement, suppressed derivation pipe, losses, speed, design pressure, built-in power, power consumption

Abstract


The paper examined SHES 'assessment of hydropower potential. To this end, based on many years of river data, hydrology was investigated and water intakes corresponding to the corresponding percentage of provision were assigned. The capacity set in accordance with the design pressure, taking into account the costs and losses received by the HES insurer, is set in annual energy consumption.

Views
111
Downloads
149

References

1. Musaev Z.S., Memmedov K.M., Zerbeliev M.S. (2019). Hydraulics and hydraulic machines. Baku,NPM “Tehsil”, p. 420

2. Designer's Handbook. Hydraulic structures / G.V.Zheleznyakov, Yu.A.Ibadzade and others under general ed. V. P. Nedrigi, M. Stroyizdat. 1983, 543 pp

3. Kiselev P.G. (1972). Handbook of hydraulic calculations, M., Energy, p.312

4. Karelin V.Ya., Volshanik V.V. (2016). Structures and equipment of small hydroelectric power stations. M.: Energoatomizdat, p.200

5. Beglyarova Zh.S. (1999). Layout of structures for small diversion hydroelectric power stations. M.,State Unitary Enterprise, p. 15

Downloads

Published

2025-10-11

How to Cite

[1]
Valiyev Jalaladdin, “STUDY OF THE HYDROELECTRIC POTENTIAL OF THE SMALL HYDROELECTIC STATION PLANNED FOR VANDAM CHAY, GABALA REGION”, SW AzUAC, no. 2, Oct. 2025, doi: 10.58225/sw.2024.2-122-127.

Similar Articles

1-10 of 86

You may also start an advanced similarity search for this article.